Rail Baltica – Neris Bridge

The bridge structures required a consistent concrete supply and carefully coordinated pours. We organised dedicated production near the site and combined mix design, delivery scheduling and quality control into one work plan.

Rail Baltica – Neris Bridge
Rail Baltica – Neris Bridge

Project details

C3’s role
Concrete production, mix design and supply coordination
Client
Project main contractor
Work period
May–August 2026
Scope of work
12,400 m³ of concrete · 18 pouring stages

Project requirements and conditions

Concrete pours had to fit around formwork, reinforcement and other contractors’ work. A supply disruption could affect an entire shift, so the contractor needed an agreed production and delivery rhythm.

The main challenge was large continuous pours, with up to 900 m³ scheduled for a single stage. Deliveries had to reach the site in sequence without extended supply interruptions.

Site access also required planning. Together with the contractor, we agreed the vehicle route, unloading points and a communication process for changes to the schedule.

Our role and solution

C3 was responsible for concrete production, mix design to the supplied technical specification and supply coordination. Structural design and concrete placement remained the responsibility of the contractor and its specialists.

We installed a dedicated mobile batching plant near the construction site. Trial mixes preceded the main works, and the contractor’s technical team helped agree the testing procedure.

Each pour had its own supply plan, covering volume, start time, vehicle sequence and responsible contacts. The plan was adjusted to actual site readiness before production began.

Quality control

Before production, we checked materials, equipment settings and the approved mix version. Batch records linked each delivery to the structure being poured.

Mix properties were checked under the agreed control plan. Sampling and test results were stored with delivery records, and deviations were reviewed with the contractor’s technical team.

One agreed communication channel kept production, transport and site teams working to the same current schedule.

Results

Over four months, we produced and supplied 12,400 m³ of concrete across 18 main pouring stages. The largest stage required 900 m³.

All 18 stages were completed against the delivery schedules agreed and updated with the contractor before work began. Each stage received a set of supply and quality-control records.

Dedicated production made it possible to plan concrete alongside construction: one team coordinated production rhythm, transport and quality control.

Contacts

Let’s discuss your project.

Leave your contact details and provide the site location. If known, add the solution you need, and we will contact you about the technical and supply conditions.

Interested in a similar solution to:

Rail Baltica – Neris Bridge

Only contact details (email or phone) and the site location are required.

Include the estimated volume, key technical requirements or any other information that will help us assess the request.

By submitting this request form, you agree to our privacy policy.

UAB „C3 Betonas“

Company code: 306056158

Registered address

V. Putvinskio g. 62, LT-44211 Kaunas

Privacy policy

© 2026 C3 Beton. All rights reserved.

Leave feedback