Akmenė – Windmill park

Twelve wind turbine foundations required large continuous pours and coordinated supply across separate work areas. We developed a foundation pouring schedule, agreed the mix properties and prepared a dedicated logistics plan for each stage.

Akmenė – Windmill park
Akmenė – Windmill park

Project details

C3’s role
Concrete production and supply for turbine foundations
Client
Energy-project contractor
Work period
June–August 2026
Scope of work
7,200 m³ of concrete · 12 turbine foundations

Project requirements and conditions

The foundations occupied separate work areas connected by temporary site roads. The contractor needed concrete production to follow foundation readiness and vehicle movements between work areas.

Each foundation required 600 m³ of concrete. Continuous placement called for consistent deliveries, making access, unloading and return routes part of the supply plan.

Site readiness and weather affected the schedule. Moving one foundation’s pour required the remaining production stages to be coordinated again.

Our role and solution

C3 organised concrete production and supply for all 12 foundations. Together with the contractor, we agreed the specified mix properties, trial mixes and readiness checks before each pour.

Before each stage, we confirmed site readiness, volume, start time and the transport route. Every pour had an agreed vehicle sequence and a named supply coordinator.

The production schedule followed the site’s receiving pace, helping prevent vehicles from queuing at one work area while leaving a gap elsewhere in the delivery sequence.

Quality control

Trial mixes checked the proposed concrete against the supplied project specification and work plan. Approved recipes and changes were recorded in the production system.

Each foundation had a separate set of delivery and quality-control documents linking the production batch, arrival time and test records.

Production and site teams reviewed conditions before each stage. Changes to the schedule or technical requirements were agreed before the next production stage began.

Results

Over three months, we supplied 7,200 m³ of concrete for 12 turbine foundations. Each foundation received 600 m³. Supply was organised into 12 main pouring stages, one per foundation.

Every stage ended with a foundation-specific set of supply and control documents, giving the contractor a single record of that foundation’s concrete works.

The key approach was a repeatable readiness process: work area, mix, transport and responsible people were agreed before every foundation pour.

Contacts

Let’s discuss your project.

Leave your contact details and provide the site location. If known, add the solution you need, and we will contact you about the technical and supply conditions.

Interested in a similar solution to:

Akmenė – Windmill park

Only contact details (email or phone) and the site location are required.

Include the estimated volume, key technical requirements or any other information that will help us assess the request.

By submitting this request form, you agree to our privacy policy.

UAB „C3 Betonas“

Company code: 306056158

Registered address

V. Putvinskio g. 62, LT-44211 Kaunas

Privacy policy

© 2026 C3 Beton. All rights reserved.

Leave feedback